Project: Garth & Minffordd Cable Sealing End Compounds – 400kV HV Plant

Key Project Details

Client:

Project: Garth & Minffordd CSEC 400kV HV Plant

Location: Garth & Minffordd

Start date:

End date:

Duration:

Contract Value:

The Challenge

Aaron HV was required to install new 400kV HV plant at the Garth and Minffordd Cable Sealing End Compounds (CSEC) to support the newly installed cable system, for which Aaron HV is also responsible. The compounds form the critical termination point for the 400kV cable circuits, so the plant had to be designed, supplied, and installed to integrate fully with the cable system and the earthing arrangements at each site. The scope covered a significant number of high-voltage components, including 24 cable sealing end structures with slip-over CTs, 12 surge arresters, 12 earth switches, associated 400kV busbar connectors, and the CSE compound earthing system, all supported by new steel structures.

What We Did

Aaron HV is providing the design, supply, and installation of all 400kV HV plant at both compounds, working as a single package with the cable installation. Our scope includes:

Design and Supply:

  • Design and supply of all equipment, including steel support structures for the compound plant
  • Design and supply of the CSE compound earthing system

Installation:

  • Installation of 24 cable sealing end structures complete with slip-over CTs
  • Installation of 12 surge arresters
  • Installation of 12 earth switches
  • Installation of associated 400kV busbar connectors
  • Installation of the CSE compound earthing system
  • Installation of steel support structures for all plant

The Outcome

  • Full 400kV HV plant package designed, supplied, and installed at the Garth and Minffordd CSECs (TBC – progress to date)
  • 24 cable sealing end structures installed with slip-over CTs (TBC)
  • 12 surge arresters and 12 earth switches installed (TBC)
  • Busbar connections and CSE compound earthing system completed (TBC)
  • Plant integrated with the newly installed 400kV cable system (TBC)

Added Value

This project demonstrates Aaron HV’s capability to deliver complete high-voltage plant packages, from design through to installation, on critical 400kV transmission infrastructure. Because Aaron HV is responsible for both the cable system and the compound plant, our teams provide a single point of accountability that improves coordination, reduces interface risk, and ensures the plant and cable systems work together as designed. The scheme supports the wider Garth and Minffordd connection, contributing to the reliable transmission capacity that underpins the energy network.